The process includes the installation of wood flooring, solid or engineered, installing the material directly over the concretly with a special adhesive and developed for this use or floating floor instalation.
Prefinish floors are ready to use once installed on site. The performance of this flooring installation is 20 to 25 m2 per day, provided that the conditions of the work a probe.
For unfinish floors, usually solid wood floors and some composites, once that has stuck to the concrete should be allowed to stabilize for at least 3 weeks. The settling time considers that the premises should remain closed with the heating operation according to a set schedule.
Once the floor has stabilized, that is, it has accommodated to the conditions of the premises and shall be deformed all it needs, we proceed to polish and vitrify (coated).
When you want more isolation and even surface, the floor can be installed on a plate that attaches to the concrete generates greater isolation. The 10mm plywood is secured with screws and dowel to the concrete. . Once you have a levelded surface, we proceed to glue down the floor to the plywood. The process is similar to the stuck on concrete, except that this is done on a wooden playwood. The stabilization process is the same.
Requirements:
Requirements for Installation of a Flooring glued directly to concrete
The process includes the installation of laminated and enginered wood flooring or prefinish compost. This type of flooring is placed on the concrete flooring, installing a loincloth that cushions the movement and serves as a moisture barrier on the floor. Installation is very quick and simple.
The installation process involves placing the glue to the dovetailing and paste a table with another pressing them together. The performance of this floor installation is 25 to 35 m2 per day, provided that the conditions are acepted. Like the laminated floor and prefinish compost comes factory finished, and once installed can be used.
Requirements:
Requirements Floating Floor Installation.
In the case of unfinished floors, that are not factory finish, once they glue in to the concrete and have stabilized, comes the polishing process. This is sandind the wood with special machines to make the flooring perfectly polished and smooth. The machines make very little dust in the process because they have a pump included.
The vitreous is the process whereby the floor, after polishing, is painted with Synteko products. These products not only seal the Lumber, they also increase their resistance to traffic characteristics and the presence of different dirt, both liquid and solid.
Normally, apply three coats of varnish on the floor.
The installation of the dust is carried out once the floor is skirting. Like the flooring, the skirting stick to l directly to the wall or in some cases using dowel and screws. Currently, the adhesives have been developed so that in many cases do not require traditional systems of installation.
Once installed, the skirting is varnished to give adequate protection and look.
The reed is installed once placed the overalls. It is used to absorb the differences in levels that takes the floor at the base where he settled. This is pasted or tipped sticks to the duster.
If the site there is a wooden floor, this should be removed. The existing floor is unused and should be revised concrete, since it can be damaged by removal of the floor, because the glue can be stronger than cement in their union.
Carpets are normally glued on the perimeter, so their removal is very simple.
Replacing carpet on wood floor should be provided as follows:
It is removed breaking the overalls, which will remain unused. There may be a deterioration in the plaster walls.
Breaking the reed is removed, which will remain unused.
Not all concrete are able to directly perform an installation. The repair will cover bite that concrete that is weak or poor adherence to glue. It also must remove those leveling with plaster or mixed cement gypsum. Then proceed to level Radierer with specific self-leveling products.